"The exact timing will depend on how work progresses in the weeks leading up to the shift, so drivers should watch for updates from ITD and check Idaho 511 before traveling."
That line comes from the Idaho Transportation Department's September 25 notice about the biggest change yet in the I-90 widening between Post Falls and Coeur d'Alene. ITD is targeting around October 20 to move both westbound lanes to the south side of the interstate. They'll sit beside eastbound traffic for a full year while crews rebuild the north side.
The ramp closures, lane drops and detours of the past few weeks can feel random. They aren't. Each one gets the corridor ready for that crossover. ITD is packing as much disruption as it can into this fall so it doesn't have to spread the same disruption across the next twelve months.
Every Closure on the Calendar Leads Up to One Switch
Here's the sequence as ITD and the City of Coeur d'Alene have published it. Dates after this week are targets, not promises.
- Oct. 2 to Oct. 9: The eastbound I-90 on-ramp from SH-41 is closed. It shut at 8 p.m. on Oct. 2. The westbound SH-41 on-ramp and both off-ramps stay open.
- Through about Oct. 12: The westbound on-ramp to I-90 from Northwest Boulevard stays closed.
- Oct. 16 to Oct. 18, tentative: Crews pave I-90 between US-95 and Northwest Boulevard, with one lane open in each direction day and night.
- Around Oct. 20: Westbound traffic crosses over to the south side.
- After the shift: Huetter Road closes beneath I-90 for up to two weeks while the old interstate bridges come down. Overnight closures of the westbound SH-41 off-ramp are expected for several weeks.
The crossover depends on the paving in step 3. The Huetter closure only happens once traffic is off the old westbound bridges. ITD built that order in on purpose: each step clears the way for the next one.
The crews also aren't starting from scratch. At the August 25 KCATT meeting, ITD reported that the crossover paving was already finished and the October 20 shift was on the schedule.
Why the Northwest Boulevard Ramp Stayed Closed Longer
The most useful detail this fall is in the City of Coeur d'Alene's September 24 update. The Northwest Boulevard westbound on-ramp closed in September for drainage work and final paving. The city's September 4 notice said that would take about two weeks. Reopening was later set for September 28. Then crews found "unforeseen issues with how the new ramp connects to the interstate."
ITD had a choice. It looked at a shorter-term fix that would have meant more closures later. Instead it extended the current closure to finish the work now, which pushed the expected reopening to October 12.
That small decision follows the same logic as the whole fall plan. Two more weeks without the ramp now replaces a second round of closures later in the construction year. If you take that ramp every morning, the delay is real. The trade is that once it reopens, it should stay open.
The ramp work also spills onto the city street. Starting September 24, the right lane of southbound Northwest Boulevard near the 76 station closes now and then so paving trucks can pull out of the I-90 work zone safely.
What the Crossover Looks Like From the Driver's Seat
Once westbound traffic moves south, ITD says you can expect:
- Two lanes in each direction
- Narrow shoulders
- Concrete barriers between eastbound and westbound traffic
- The westbound rest area closed to all traffic, including commercial vehicles
- The eastbound rest area still open
Lane count is the part that matters most. With two lanes still open each way, the crossover doesn't take capacity away during normal traffic. What changes is the margin for error. With narrow shoulders and concrete barriers, a stalled car or a fender bender has nowhere to pull over. That stretch runs between SH-41 in Post Falls and US-95 in Coeur d'Alene.
The year-long timeline matters too. If the switch lands near the target, this layout should hold until about fall 2027. The lane pattern you learn in late October is the one you'll drive through winter, spring and next summer's lake traffic.
The Huetter Weeks
The one big closure after the crossover is at Huetter Road. ITD says Huetter will close beneath I-90 for up to two weeks after traffic shifts, while crews demolish the existing interstate bridges. No fixed start date has been published.
ITD's suggested alternate routes depend on which side of the freeway you start from:
| If you're coming from | ITD's suggested route |
|---|---|
| North of I-90 | Mullan Avenue, or Poleline Avenue/Hanley Avenue |
| South of I-90 | Seltice Way |
Plan for some overlap here. The City of Coeur d'Alene expects its Mill River Lift Station upgrade to run through mid-November. That means intermittent closures with one lane open each way on Grand Mill Road, and the city has pointed drivers to Huetter Road as an alternate. If the Huetter closure under I-90 starts shortly after October 20, both projects will be active in the same part of west Coeur d'Alene for part of the same window. Neighbors around Mill River who already use Huetter to get around Grand Mill Road may find themselves rerouting a second time.
Off the Freeway: the Centennial Trail Closure
One more closure overlaps the run-up to the crossover. A two-mile section of the North Idaho Centennial Trail, from Pleasant View Road east toward Spokane Street, is closed September 23 through October 14 for asphalt replacement. The Coeur d'Alene Press reported the cost at $280,051.
That section is on the Post Falls end of the trail, not inside Coeur d'Alene city limits. Still, anyone who bikes the corridor parallel to I-90 should know the trail reopens a few days after the Northwest Boulevard ramp and a few days before the target crossover date.
Where This Year Fits in the Bigger Project
The crossover is a big step, but it's still the middle of the project. ITD describes the job as five miles from SH-41 to US-95, adding two lanes in each direction for four lanes each way. Crews are replacing and widening the I-90 bridges over Huetter Road, Atlas Road and Prairie Trail. They're also lengthening every ramp at Northwest Boulevard, plus the eastbound and westbound off-ramps at US-95.
Construction started in August 2025, and ITD expects it to take four years and finish in 2029. The estimated cost is about $200 million to $210 million in 2025 dollars, including design, right-of-way and construction.
The project page doesn't list a full rebuild of the US-95 interchange. That's a separate project still in design, and ITD expects its construction to begin in 2027. So the north-side rebuild starting this October and the US-95 interchange work are expected to overlap at some point next year.
What hasn't been announced is a winter work pause. ITD's current project page describes typical weekday work, day and night, with possible weekend work, and gives no winter shutdown date. When construction began in August 2025, ITD said work would continue through fall and winter. That release is more than a year old, and the agency hasn't confirmed the same plan for this winter.
The Dates Most Likely to Move
Two dates are fixed enough to plan around this week: the SH-41 eastbound on-ramp reopening on October 9 and the Northwest Boulevard westbound on-ramp reopening by October 12. Everything after that is tentative by ITD's own description. That includes the October 16 to 18 paving, the crossover around October 20 and the Huetter closure that follows. The Northwest Boulevard ramp has already moved once, from September 28 to October 12. Check the ITD project page and Idaho 511 before any trip you can't afford to be late for.
If you're thinking about listing a home near Huetter, Northwest Boulevard or the Mill River area during the crossover year, construction traffic and detours will affect showings. Plan around it from the start. ExSell Realty Group can walk you through timing and pricing with this corridor's schedule in mind. Start with a Free Home Valuation.